Sunday, 21 February 2010

In several places at once

So called because this post is going to be a collection of 'bits' that have happened over the last few weeks.

Let's start of with my old favourite, the Settle - Carlisle line.

In April we are going to start what should be the last bit of major track renewal needed on the line to replace most of the old jointed track with continuously welded rail (CWR). We are replacing 23 miles of track at 22 different locations. Much of the work will be on the northbound line, north of Appleby but there are also seven sites south of the town and all that work will be on the southbound line.

All the work is being done overnight during the week, so minimising disruption to passenger trains and doing away with the need for a complete line closure as has been the case in the last two or three years - so no more Ribblehead Viaduct public walks!

The work will finish in September.

We are using the New Track Construction train, which virtually lays the track in front of itself as it goes along. Take a look at the photos below. Not sure that I would want to be the 'operative' that you can just make out in his hi-vis gear inside the machinery in the photo on the right.












On a much smaller scale we move to Earlestown, a station on the fringes of what is called Merseyside. It's an unusual station in that it has a triangular island platform. Platforms 1 and 2 are on the Manchester - Liverpool line, platforms 4 and 5 are electrified as they privide a link to the west coast main line. They are also used by the Arriva Trains Wales diesel service between Wales, Chester and Manchester. Platform 3 is largely unused (I think, but I am open to correction).

We are part way through a project to completely rebuild platforms 4 and 5. Our contractor J Murphy & Sons is working on one end of each platform while the trains use the opposite end. Fortunately the platforms are long enough to be able to do that otherwise it would have meant closing the platforms completely. Platforms are being surfaced in tarmac and the photo on the left shows the steam rising while Murphy's people work on it. The photo on the right is the 'southbound' platform under construction.


From Earlestown, we stay on Merseyside but move north to Southport where we are strengthening one of the main road-over-rail bridges to the east of the town.

The road is the A5267 which carries St Lukes Road over the Southport to Wigan line. Nearly 19,000 vehicles use it each day, of which just over 450 are HGVs - and that is the problem. The bridge has failed its structural assessment based on modern criteria. That doesn't mean it is about to fall down, it just doesn't meet the latest standards required to allow 40 tonnes lorries to use it. If the work isn't done, the highway authority (Sefton Council) would have to impose weight restrictions which would mean HGVs would be banned as would larger emergency vehicles sich as ambulances and fire appliances.

The bridge has three spans. The deck of one span is to be replaced, an additional supporting pier will be built in between the train tracks effectively dividing the main span in two and the footpaths over the third span are to be strengthened to withstand an HGV mounting the pavement.

The photo on the left shows the road with bollards to keep vehicles off the pavements. The other photo show us doing our bit for butterfly conservation by providing buddleia for them to feed on.












The final bit of this post brings us right up to date with the publication last Tuesday of the Northern Hub study by Network Rail. This is our part of what started out as the Manchester Hub study by The Northern Way, which is an amalgamation of three separate regional development agencies covering most of the north of England. They put together their thoughts on what transport developments would be needed to sustain and build the economy and we have turned their aspirations into reality.

In simple language, we can do it all for £530m, primarily by building two additional platforms at Manchester Piccadilly station; building an additional curve line in Ordsall, Salford which will provide a direct link between Victoria and Piccadilly stations; building some additional passing loops at various places; reopening two of the closed bores of Standedge Tunnel.

If you want to find out more, take a look at my news release where you will find the 8-page summary brochure that you can download. There is also some fancy CGI that you might want to look at. The full 85-page brochure is also on the Network Rail website.

Friday, 29 January 2010

Cheadle Hulme in for an upgrade

Network Rail has put plans before Stockport council for a major upgrade at Cheadle Hulme station under the DfT's Access for All programme.

The station straddles the railway line south of Stockport where it splits to go towards Macclesfield and Stoke in one direction and towards Wilmslow and Crewe in the other. As such, it has four platforms - platform one serves trains from Crewe/Wilmslow northbound to Stockport/Manchester; platform 2/3 is a triangular island platform (2 southbound towards Wilmslow and Crewe, 3 northbound from Stoke/Macc); platfrom 4 takes people south towards Stoke/Macc.

The ticket office is at road level, some eight metres below the platforms which are constructed on an embankment, and the only way to reach the trains is via stairs. This is makes the station a no-go area for anyone in a wheechair and difficult for the elderley and people with buggies or lots of luggage.

The idea therefore, assuming the plans are passed by the council, is to build lift towers on all platforms leading to an overbridge. There will also be direct access to the station car park which is adjacent to platform 4.

If all goes according to plan, the work contract will be let around Easter, we will start on site in the autumn and complete early in 2011.

Thursday, 28 January 2010

BBC Countryfile

I found myself back on the Settle - Carlisle line again on Tuesday. The BBC Countryfile team found out that the line had been named as number 2 in the 10 greatest railway journeys of the world by ABC News in New York so they arranged to do some filming on the line.

They spoke to Mark Rand, the Chairman of the Friends of the Settle - Carlisle Line, then travelled from Settle to Ribblehead on a Northern train. I met them at Ribblehead, together with Network Rail's mobile operations manager Steve Marney, and we drove part way to Blea Moor signal box, before completing the last 400 metres on foot - something the signaller has to do every day.

They wanted to go into the signal box because some claim it is the most remote on our network, and interview the signaller about his work in such a location.

The signaller on duty was Jay Hartley, one of the relief team that works the line and he gave a very good account of the job etc. to presenter Julia Bradbury.

The programme is due to be broadcast on Sunday 7 Feb on BBC TV.





Wednesday, 20 January 2010

More snow pics ....

.... although strictly speaking these are icicles rather than snow.

Supplied by Gorden Allen, Network Rail's track maintenance engineer based in Appleby (Cumbria) they were taken on 9 Jan inside Blea Moor and Rise Hill tunnels on the Settle - Carlisle line. They form round the ventilation shafts from natural water seepage rather than from snow and ice melting out in the open air and dripping down.

As well as icicles there is also a build up of ice at track level.

The first three are Blea Moor, the last is Rise Hill.




Tuesday, 12 January 2010

Workington viaduct scour protection

My third post of the day (a picture paints a thousand words, they say, so from now on the emphasis is on photos).

Just completed dumping nearly 2,500 tonnes of stone at the foot of the piers holding up Workington railway viaduct. The stone will act as a breakwater and reduce the effects of floodwater and debris should the worst happen again.











Alderley Edge bypass

One of the major jobs that Network Rail carried out over the Christmas holiday was to complete the building of a  bridge that will carry the Crewe - Manchester railway line over what will soon become the A34 Alderley Edge bypass. We carried out all the prep work in Christmas 2008 and the job last Christmas was to slide the bridge deck into position.

All went according to plan and the railway was handed back for train running four hours ahead of schedule.

Thought you might like to see a few photos to give you an idea of the scale of the project.

The first couple show the bridge deck being inched into position on multi-wheeled 'jacks' working in tandem.

The third shows a Virgin Pendolino train passing over the new bridge, but my favourite is the last one. 








This is a view looking down into one of the support pillars that hold the bridge up. It is so huge and so deep that the last bit of excavation had to be done by lowering a mini digger - and operative - into the pillar.

Rather him than me!

Snow pics

No, not the sort you use to climb Everest, just a few shots taken by Network Rail people over the last week to give an idea of what it was like in the North West.


The first couple show Guide Bridge signal box and a train passing though Guide Bridge.










Next is Earlestown (left) and a group of our staff working in the Thatto Heath area.













Then we have Ais Gill on the Settle - Carlisle line, and one of frost crystals on a railway sleeper.












Finally, one of a set of point heaters, doing exactly what they are supposed to do - keep the moving parts of a set of points free from freezing up.